Engineering Systems Monitoring, Transportation Safety System at the Levashovo Airport Complex in St. Petersburg

Installation of a structured monitoring and control system for the engineering systems of buildings and structures, as well as a transportation safety system for the overpass at the exit leading to the airport complex at Levashovo Airfield in St. Petersburg

  • Project description:

    As part of phase IV of the construction of the airport complex at Levashovo Airfield, STC “IMS” carried out a full range of work on the installation of transportation safety systems at the “Overpass at Exit C2” facility, which provides a connection to the A-118 federal public highway, the Ring Road around St. Petersburg. The structure is part of the highway leading from the airport complex and is of strategic importance for the transportation accessibility of the region’s air gateway.

    The overpass is classified as a federal-level transportation infrastructure facility and requires strict compliance with the provisions of Federal Law No. 16-FZ, as well as industry regulations and safety standards, at all stages of construction and installation work.

  • Project objectives:

    Construction and installation work:

    • A work execution plan was developed, with all necessary approvals obtained from the Contractor, General Contractor, and Client to ensure uninterrupted construction;
    • Work areas have been set up for equipment installation, with subsequent dismantling upon completion of the work;
    • Security television (video surveillance) systems have been installed to provide round-the-clock monitoring of the perimeter and areas of responsibility;
    • Information collection and processing systems have been installed to integrate data with higher-level situation centers;
    • A comprehensive set of works has been completed on the installation of cable ducts, including the laying of polyethylene pipes, the installation of protective casings, and the construction of cable manholes;
    • Fiber-optic communication lines have been installed for high-speed data transmission between transportation safety system components;
    • A full cycle of work has been completed on the installation of power supply systems for security equipment: laying power cables, installing connection joints, and performing commissioning and start-up work.

    Quality and reliability control:

    A comprehensive set of tests was conducted on the materials used and the finished structural elements, confirming that the installed systems comply with design specifications and operational reliability requirements.

    The STC “IMS” comprehensive approach to organizing construction and installation work –Including the preparation of work execution plan, the creation of temporary infrastructure, and subsequent testing – ensured the high-quality installation of transportation safety systems on the overpass within a tight timeframe. The implementation of the project at a site adjacent to one of St. Petersburg’s busiest thoroughfares has reaffirmed the company’s status as a reliable contractor for work on critically important federal-level road and airport infrastructure projects.

  • Implementation period: 2023 year

Used solutions

KSM.Flow

KSM.Flow

Automated Traffic Control System

Read more

Used equipment