Structural Health Monitoring System of the Moscow–Nizhny Novgorod–Kazan highway, phase 6, 7, 8
Installation of the hardware and software complex of the structural health monitoring system on the Moscow–Nizhny Novgorod–Kazan highway, phase 6, 7, 8
-
Project description:
Execution of a comprehensive set of installation and commissioning works for the implementation of the hardware and software complex of the structural health monitoring system and for the power supply of the SHMS of the bridge crossings across the Volga River, the Sura River, the Sviyaga River, and the Osipov Ravine at the following site: M-12 “Moscow–Nizhny Novgorod–Kazan highway (under construction),” phase 6, 7, 8.
The measurement system included several types of sensors:
- mechanical strain sensors (vibration strain gauges);
- biaxial inclinometers;
- displacement sensors;
- accelerometers;
- temperature sensors;
- anemometric station.
-
Project objectives:
- Installation of a structural health monitoring system.
- Supply of equipment, materials, and software.
- Construction, installation, and commissioning work.
- Inspection and acceptance tests.
-
Implementation period: 2022 – 2025 years
Used equipment
- office 408, 4, lit. K, Fuchika St., St. Petersburg, 192102, Russia
- +7 (812) 775-10-82
- office@ntc-ksm.ru